OCIC Office Building Progress Record

April 2020


STRUCTURE WORK : Done.
MEP WORK : Equipment installation done. T & C in progress.
ARCHITECTURAL WORK : Facade painting, louver and green wall installation in done. Internal work remaining painting, ID works and De-snag.
EXTERNAL WORK : De-snag for Ground Floor external soft scape and landscape.


February 2020


STRUCTURE WORK : Done.
MEP WORK : Equipment installation in progress, start testing and commissioning.
ARCHITECTURAL WORK : Facade painting, louver and green wall installation in progress. Internal building starts cleaning and snagging.
EXTERNAL WORK : Ground Floor external soft scape and landscape in progress.


December 2019


STRUCTURE WORK: Done.
MEP WORK : MEP 1st fix done and 2nd Fix L20 & L21, MEP Work 3rd Fix L6 to L8.
ARCHITECTURAL WORK : External Plastering Up to L18, Wet work (tiling) at G to L17, Painting work in progress (Skim coat) L1 to L15.
EXTERNAL WORK : Fencing foundation in progress.


October 2019


STRUCTURE WORK : L21 column and core wall in progress.
MEP WORK : MEP 1st fix up to 21F and MEP 2nd fix up to L18.
ARCHITECTURAL WORK : Installing block wall up to L18, Plastering work up to L8 Waterproofing up to L9, Tiling work at GF toilet.
EXTERNAL WORK : Shift rebar yard for external sub base and facing work.


August 2019


STRUCTURE WORK : L19 in progress.
MEP WORK : MEP 1st fix up to 19F and MEP 2nd fix up to L12.
ARCHITECTURAL WORK : Wet trade at G to L8, (block installation), Plastering L3 & 5F.


June 2019


STRUCTURE WORK : Construction stage of Super Structure (15th floor Slab form In Progress). The main activity is concrete structure work.
MEP WORK : MEP 1st fix up to 15F, MEP 2nd fix up to 5F.


April 2019


STRUCTURE WORK : Construction stage of Super Structure (12th floor Slab form In Progress). The main activity is concrete structure work.
MEP WORK : MEP 1st fix up to 12F.


February 2019


STRUCTURE WORK : Construction stage of Super Structure (6th floor). The main activity is concrete structure work.
MEP WORK : MEP 1st fix up to 6F.


December 2018


STRUCTURE WORK : Construction stage of Super Structure (2nd floor in progress).
MEP WORK :1st fix up to 2F.


October 2018


STRUCTURE WORK : Construction stage of Super Structure (GF column and core wall).
MEP WORK : MEP 1st at GF.


August 2018


Ground floor slab done.
GF to 1F core wall and column rebar installation in progress.
Soil: leveling for external soil.


June 2018


MEP underground work in progress.
Substructure works (pile cap, STP tank and underground water tank) in progress and soil back filling.


April 2018


Pile load test done.
Excavation pile cap and pile head cup.


February 2018


Bore pile works in progress.


December 2017


Mobilize machinery to start bore pile work.


2019.11.30