OCIC Office Building In Progress

November – December 2019

STRUCTURE WORK: L21 column and core wall in progress SYSTEMS INSTALLATION: Fix L2 to L18 ARCHITECTURAL WORK: Installing block wall up to L18 Plastering work up to L8 Waterproofing up to L9 Tiling work at GF toilet

September – Octomber 2019

STRUCTURE WORK: L19 in progress SYSTEMS INSTALLATION: MEP Work at G to L12 ARCHITECTURAL WORK: Wet trade at G to L8 (block installation), Plastering L3 & 5F

 

July – August 2019

Construction stage of Super Structure (15th floor Slab form In Progress). The main activity is concrete structure work.

 

May – June  2019

Construction stage of Super Structure (12th floor Slab form In Progress). The main activity is concrete structure work.

 

March – April 2019

Construction stage of Super Structure (6th floor). The main activity is concrete structure work.