L’attrait Boeung Keng Kang in Progress

June 2020


STRUCTURE WORK: Completed
MEP WORK: • Studio – above ceiling services completed & testing in progress
• 1 Bed, 2 Bed, Penthouse – above ceiling services & Wall conceal in progress
ARCHITECTURAL WORK: • Studio – Interior Finishing in progress
• 1 Bed, 2 Bed, Penthouse – Wet trade block & Plastering in progress
EXTERNAL WORK: External plastering, external window frame & glazing and balcony handrail installation in progress


April 2020


STRUCTURE WORK: L25 / L26 + Rooftop on going
MEP WORK: In progress from L1 to L21
ARCHITECTURAL WORK: L4 to L21 in progress
EXTERNAL WORK: L4 to L11 in progress


February 2020

 

STRUCTURE WORK: L20 in progress
MEP WORK: L17 in progress
ARCHITECTURAL WORK: L4 to L14 in progress

 

December 2019

 

STRUCTURE WORK: L15 in progress
MEP WORK: L11 in progress
ARCHITECTURAL: WORK L4 to L11 in progress
Mock up unit completed

 

October 2019

 

STRUCTURE WORK: L13 in progress
MEP WORK: L10 in progress
ARCHITECTURAL WORK: L4 to L11 in progress
Mock up unit in progress

 

August 2019


STRUCTURE WORK: L12 in progress
MEP WORK: L10 in progress
ARCHITECTURAL WORK: L4 to L7 in progress
Mock up unit in progress


June 2019


STRUCTURE WORK: L9 in progress
MEP WORK: L5 in progress
ARCHITECTURAL WORK: L4 to L5 in progress


April 2019


STRUCTURE WORK: L7 in progress
MEP WORK: L1 to L7 in progress


February 2019


STRUCTURE WORK: L4 in progress
MEP WORK: L1 to L4 in progress


December 2018


STRUCTURE WORK: L3 in progress
MEP WORK: L1 to L3 in progress


October 2018


Sub structure works in progress – Shoring, excavation, footing, pile cap, tie beam, underground water tank, elevator pit, car lift pit.


June 2018


Bored pile – PIT, Sonic test, sheet piling for protection of excavation works.


April 2018


Bore pile works in progress


2020.04.23