Hattha Bank Tower In Progress

October 2022

ANK TOWER: Construction of 5th Floor Slab completed Blockworks and 2nd Fix MEP Works in GF 1st Floor, 2nd Floor, and 3rd Floor in progress
PARKING BUILDING: Construction of Mezzanine Floor in progress
GENERAL AREA: Construction of External Under Ground MEP Works in progress

August 2022

BANK TOWER: 3rd Floor Slab Works in Progress
PARKING BUILDING: Backfilling Works for GF Slab in Progress
GENERAL AREA: Plastering Works for Boundary Wall in Progress

 

June 2022

BANK TOWER: 3rd Floor Slab Works in Progress
PARKING BUILDING: Backfilling Works for GF Slab in Progress
GENERAL AREA: Plastering Works for Boundary Wall in Progress

 

April 2022

BANK TOWER: 1st Floor Slab Completed
2nd Floor Slab in Progress
PARKING BUILDING: Backfilling for GF Slab in Progress
GENERAL AREA: Blockworks for Boundary Wall Completed

February 2022

BANK TOWER: Ground Floor Slab Works in Progress
PARKING BUILDING: Pile Cap Works in Progress
GENERAL AREA: Blockworks for Boundary Wall in Progress 

 

December 2021

MAIN BUILDING: Pile Cap Works in progress
PARKING BUILDING: Pile Cap Works in progress
GENERAL AREA: Foundation for Boundary Wall in progress

 

September 2021

BANK TOWER: Bored pile works in progress
PARKING BUILDING: Spun Pile works in progress

 

July 2021

Groundbreaking Ceremony: 05 July 2021

Learn more about groundbreaking ceremony

Mobilization of equipment for site clearing and levelling works.

 

January 2021

Status: contract signed off

Official Contract Signing Ceremony: 27 January 2021

Learn more about signing ceremony

 

2021.02.02